Actual cost of work performed |
|
|
The actual cost of work performed to accomplish a task, whether or not the task itself is complete. |
|
|
|
|
Accrued expenditures |
|
|
Expenditures for which it is known that payment will be made, but for which payment has not actually been made. |
|
|
|
|
Funding authorized to date |
|
|
Funding amount which has been authorized to be expended. |
|
|
|
|
Budgeted cost of work performed |
|
|
The cost that was budgeted for tasks that have been completed, regardless of the actual cost of completing those tasks. |
|
|
|
|
Budgeted cost of work scheduled |
|
|
The amount budgeted for completion of a task or tasks. |
|
|
|
|
Cost adjustment |
|
|
An adjustment to an existing cost. |
|
|
|
|
Contract work authorized and defined |
|
|
The cost of contract work that has been both authorized and defined by the contractee. |
|
|
|
|
Estimated amount |
|
|
An amount that has been estimated. |
|
|
|
|
Funds carry-over |
|
|
Funds that have been authorized for use within a prior fiscal period that had not been spent and are being added to the existing fiscal period. |
|
|
|
|
Forecast of billings |
|
|
An estimate of costs that will be billed to the contractee at a future date. |
|
|
|
|
Forecast of not yet authorized funding |
|
|
An estimate of future funding that has not yet been authorized by the contractee. |
|
|
|
|
Contract work authorized but not definitized |
|
|
Work on a contract that has been authorized by the contractee but for which the scope has been fully determined. |
|
|
|
|
Non-recurring |
|
|
Costs that are single occurrence. |
|
|
|
|
Open contract commitment |
|
|
An estimate of costs that the contractor is obligated to pay. |
|
|
|
|
Open contract commitment, cancellable |
|
|
An estimate of costs, excluding accrued expenditures, that the contractor can make void if the contract does not continue to completion. |
|
|
|
|
Open contract commitment, non-cancellable |
|
|
An estimate of costs, excluding accrued expenditures, that the contractor cannot make void if the contract does not continue to completion. |
|
|
|
|
Forecast of funding for all other work |
|
|
An estimate of future funding for all work not otherwise defined. |
|
|
|
|
Recurring |
|
|
Costs that recurr on a periodic basis. |
|
|
|
|
Schedule adjustment |
|
|
An adjustment to a schedule. |
|
|
|
|
Costs to terminate the contract |
|
|
The amount contractually defined to be paid by the parties of the contract in the event of contract termination. |
|
|
|
|
|
|
Reprogram variance cost adjustment |
|
|
An adjustment to cost variance in the event of reprogramming the budget baseline of a project. |
|
|
|
|
Reprogram variance schedule adjustment |
|
|
An adjustment to schedule variance in the event of reprogramming the budget baseline of a project. |
|
|
|
|
Mutually defined |
|
|
Mutually agreed upon cost management code. |
|
|
|
|
Authorized Baseline Changes |
|
|
The amount that was authorized for baseline changes. |
|
|
|
|
Total Budget Reprogramming |
|
|
The total of all budget reprogramming |
|
|