Planning Level_ Code. Type/Code. Content |
|
Full CL |
|
|
|
|
|
|
Activity |
|
Tasks or work effort that will be completed over time. |
|
|
|
Control Account |
|
A management control point for planning and control as it represents the work associated with one project work breakdown structure element that is assigned to one responsible organizational entity. |
|
|
|
Planning Package |
|
A logical aggregation of future work within a control account that has not yet been planned in detail at the work package or task level. |
|
|
|
Summary Level Planning Package |
|
Future work effort assigned to a higher level account. |
|
|
|
Work Package |
|
A task or set of tasks performed within a control account. |
|
|
|
Mutually Defined |
|
Mutually agreed upon planning level code. |
|