A character string used to represent or replace the type of earned value calculation method.
  
Obj.ClassQual. 
  
Earned Value Calculation Method
  
Obj.ClassTerm 
  
Code
  
Occurrence
  
1..1
  
Codes
  
APF
Apportioned effort
Earned value dependent on other discrete tasks being completed.
  
LOE
Level of effort
Earned value is based on the level of effort in the absence of specific end results or deliverables, such as management and other non discrete work tasks.
  
MTN
Milestone
Earn a specified percent complete (of the total budget) when a milestone is complete.
  
P01
Work complete
Earn 100% of the budget value when the work effort is complete.
  
P10
Work start
Earn 100% of the budget value when the work effort begins.
  
P50
Half start
Earn 50% of the budget value when work begins, earn remaining 50% when work completes.
  
PLN
Package planning
Not an earned value method per se, but used to identify a task or work package that must be broken down into discrete work effort at a later time.
  
PTC
Percent complete
Earned value is based on the percent complete (between 0 and 100).
  
STD
Standards
Earned value is based on a set standard defined for the type of product being produced.
  
UNT
Units
Earned value is based on quantity of material units or manufactured components.
  
ZZZ
Mutually defined
Mutually agreed upon earned value calculation method.