Cost Management_ Code. Type/Code. Content
Full CL
CC
Code. Content
 
 
  
ACP
  
Actual cost of work performed
The actual cost of work performed to accomplish a task, whether or not the task itself is complete.
  
AE
  
Accrued expenditures
Expenditures for which it is known that payment will be made, but for which payment has not actually been made.
  
AF
  
Funding authorized to date
Funding amount which has been authorized to be expended.
  
BCP
  
Budgeted cost of work performed
The cost that was budgeted for tasks that have been completed, regardless of the actual cost of completing those tasks.
  
BCS
  
Budgeted cost of work scheduled
The amount budgeted for completion of a task or tasks.
  
CA
  
Cost adjustment
An adjustment to an existing cost.
  
DAW
  
Contract work authorized and defined
The cost of contract work that has been both authorized and defined by the contractee.
  
EST
  
Estimated amount
An amount that has been estimated.
  
FC
  
Funds carry-over
Funds that have been authorized for use within a prior fiscal period that had not been spent and are being added to the existing fiscal period.
  
FOB
  
Forecast of billings
An estimate of costs that will be billed to the contractee at a future date.
  
NAF
  
Forecast of not yet authorized funding
An estimate of future funding that has not yet been authorized by the contractee.
  
NDW
  
Contract work authorized but not definitized
Work on a contract that has been authorized by the contractee but for which the scope has been fully determined.
  
NRC
  
Non-recurring
Costs that are single occurrence.
  
OC
  
Open contract commitment
An estimate of costs that the contractor is obligated to pay.
  
OCC
  
Open contract commitment, cancellable
An estimate of costs, excluding accrued expenditures, that the contractor can make void if the contract does not continue to completion.
  
OCN
  
Open contract commitment, non-cancellable
An estimate of costs, excluding accrued expenditures, that the contractor cannot make void if the contract does not continue to completion.
  
OF
  
Forecast of funding for all other work
An estimate of future funding for all work not otherwise defined.
  
REC
  
Recurring
Costs that recurr on a periodic basis.
  
SA
  
Schedule adjustment
An adjustment to a schedule.
  
TC
  
Costs to terminate the contract
The amount contractually defined to be paid by the parties of the contract in the event of contract termination.
  
TOT
  
Total
Total costs.
  
VCA
  
Reprogram variance cost adjustment
An adjustment to cost variance in the event of reprogramming the budget baseline of a project.
  
VSA
  
Reprogram variance schedule adjustment
An adjustment to schedule variance in the event of reprogramming the budget baseline of a project.
  
ZZZ
  
Mutually defined
Mutually agreed upon cost management code.
  
ABC
  
Authorized Baseline Changes
The amount that was authorized for baseline changes.
  
TBR
  
Total Budget Reprogramming
The total of all budget reprogramming